Tower A is now two-thirds of the way up, and the façade mock-up has been signed off.
On 12 October the site team poured the 17th-floor slab of Tower A, keeping Ocean View Residences on programme for handover in December 2027. Tower B has reached level 12.
Façade and glazing
The full-size façade mock-up was approved by the architect and the client representative in September. Low-E double-glazed units for the sea-facing elevations are now in production, with the first deliveries due in January.
What happens next
Over the next quarter, mechanical and electrical works move up from the 8th floor, the podium pool shell is water-tested, and the show-apartment finishes are repeated in the first completed homes.
Buyers can follow every stage on the construction progress page, which is updated with new photographs on the first working day of each month.