Updated on the first working day of each month
On site this month
Every project under construction, with photographs and the percentage complete certified by the project architect.
Mount Lavinia · completion Dec 2027
Project detailsOcean View Residences · 62%
- Oct 202662%17th floor slab poured in Tower A. Tower B at level 12.Tower A 68% · Tower B 54%
- Sep 202658%Façade mock-up approved. Glazing order placed.Tower A 64% · Tower B 50%
- Aug 202654%Pool deck waterproofing complete on the podium.Tower A 59% · Tower B 47%
- Jul 202650%8th floor slab handed over to MEP contractors.Tower A 55% · Tower B 43%
- Jun 202646%Tower B core reaches level 10.Tower A 50% · Tower B 40%
- May 202641%Basement car park slab complete.Tower A 45% · Tower B 36%
Colombo 03 · completion Jun 2028
Project detailsThe Marine Crest · 38%
Monthly photo sets for The Marine Crest start with the next update. Subscribe at the foot of this page to receive them by email.
View The Marine CrestNegombo · completion Mar 2027
Project detailsLagoon Terraces · 81%
Monthly photo sets for Lagoon Terraces start with the next update. Subscribe at the foot of this page to receive them by email.
View Lagoon Terraces